EAST GRAND RAPIDS, Mich.—Road construction is in full swing in East Grand Rapids this week.

According to the city, at least four road projects will be taking place this week, including resurfacing of and renovations to Monterey Drive, Gladstone Avenue, Rosewood Alley and Reeds Lake Boulevard. 

Work on Monterey Drive should be finished within two weeks; the Gladstone and Rosewood projects should take about three weeks to complete.  Repairs to Reeds Lake Boulevard should take about a month.

Crews are also expected to begin work on Bellclaire Avenue from Lake Drive SE to Frederick Drive SE on Monday, August 12.  That project should be complete within three weeks.

For more project information, call the City Engineering Department at (616) 940-4817.